|
1
|
- Presentation to the Joint Committee
- on the Public Schools
- October 3, 2005
- Dr. H. Gordon Pethick, Superintendent
- Mr. Roderick Pianelli, Board of Education President
- Dr. Jacqueline R. Attinello, Assistant Superintendent
|
|
2
|
- Located in Warren County Northwest part of state
- Population of 16,000 within 3.2 square miles
- Previous major employers
- Ingersoll Rand
- Baker Chemical
- Bell and Howell
- Bethlehem Steel
- Economic Status: 64% of households earn less than $50,000 per year
- 38% of students are on free or reduced lunch
- 135 year sending/receiving relationship with five communities
- Positive academic growth/redevelopment efforts
|
|
3
|
|
|
4
|
- Presently - 3,500 students are located at ten sites (including armory
& spaces in neighboring district).
- Forty-one (41) TCUs/trailers (Pre-K -12)
- Elementary – 7 trailers
- Middle School – 3 trailers
- High School – 31 trailers (1,675 students/1,243 “unhoused”)
- 1998 Long Range Facilities Plan (LRFP) proposed a new high school and
other recommendations (additions, renovations) impacted by grade
reconfiguration.
- LRFP was approved by NJDOE on January 31, 2001.
|
|
5
|
- Built in 1927
- Addition in 1959
- 2005 enrollment is 1,675 students
- 40% of students are housed in trailers
- September 2008 projected enrollment is 1,964 students
- New school to house 2,000 students
|
|
6
|
|
|
7
|
- Thirty-one (31) TCUs/trailers
- 40% outside
- Health
- Safety
- Security
- Larger class sizes in core subjects
- Difficulty in meeting Core Curriculum Content Standards
- Inadequate core facilities
- Labs
- Science
- Family & Consumer Science
- Industrial Tech
- Technology
- Art Rooms
- Music – vocal and instrumental
- Library/Media Center
- Physical Education
- Cafeteria – five (5) lunch periods
- Auditorium (capacity 600)
- Gym (capacity 1,150)
|
|
8
|
|
|
9
|
|
|
10
|
|
|
11
|
|
|
12
|
|
|
13
|
|
|
14
|
|
|
15
|
- September 1996 – Four (4) used trailers purchased and installed
- September 1998 – Two (2) new trailers purchased and installed
- February 2000 – PSD lease-purchased property for the high school site
($2,100,000)
- January 2001 – NJDOE approved the district’s LRFP and designated money
to fund all district construction including $48.5M for the new high
school
|
|
16
|
- May 2001- October 2003 –PSD pursued status as Demonstration Project
- September 2002 – Six (6) new trailers purchased and installed
- December 20, 2002 - EDA/SCC purchased the property for the high school
site for $2.2M
- September 2003 – Nine (9) new trailers lease/purchased and installed
|
|
17
|
- March 2004 – architect (NJK12) received Notice to Proceed on high school
project
- April 2004 – PSD began meeting with SCC every 2 weeks in West Paterson
- September 2004 – Ten (10) new trailers lease/purchased and installed
(Clark St. closed)
- October 2004 – NJDOE transmitted their approval of high school project
to NJEDA/NJSCC*
|
|
18
|
- March 2005 – Construction documents (100%) were submitted to NJDCA by
the architect
- May 2005 – Notice to Proceed with site work (Phase #1) was issued by the
SCC
- June 2005 – Site work (Phase #1) began on the high school project
- June/July 2005 – PSD assured by SCC that the high school building was in
the “queue” and would continue as scheduled, bids would be accepted in
September 2005, with the opening for September 2008
|
|
19
|
- July 2005 – SCC letter to PSD
- Failed to approve high school building (Phase #2) in the list of
projects for remaining funds, *
- Noted recommendation - “access roads for high school should not be
built.”* (construction on the road and other site work had been
underway for two months $35,000 per day)
|
|
20
|
- High School Project met necessary criteria
- Overcrowding
- Health and Safety
- Well along in design process
- Acquired property
- Phase #1 (Site work one of original 59)
- DOE representative recommended removing Phase #1 because there was no
money to fund the high school building
- Nineteen (19) of the 59 projects approved do NOT have property
|
|
21
|
- $2,200,000 - land acquisition
- $180,000 - environmental studies
- $10,000 - engineering fees
- $4,275,000 - architectural fees
- $1,875,000 - trailers (“swing space”)
- $7,600,000 - site work (December 2005)
- $16,140,000 - 2005 TOTAL
|
|
22
|
|
|
23
|
- 2009 - by NJDOE definition = 1800
unhoused students
- Inability to meet NJCCS
- Health and safety issues
- Deteriorating trailers
- Exposure to the elements
- Safety and security
- Increased construction costs for school
- 2001 estimate - $48,500,000
- 2005 estimate - $95,000,000
- 2009 estimate - $?
|
|
24
|
- ALL students in NJ deserve adequate facilities in which to attend
school.
- Abbott initiatives have helped non-Abbott districts, too.
- Abbott students should not be held hostage for the mistakes of the
various state agencies responsible for implementing the Educational
Facilities Construction and Financing Act.
- State needs to keep its promise to its children.
|